Follow

How do I change the start day of the week in my Calendar?

In Microsoft Outlook 2007

  1. On the Tools menu, click Options.
  2. Click Calendar Options.
  3. Under Calendar work week, in the First day of week list, select the day that applies to both the full week and the work week.

 

In Microsoft Outlook 2010

  1. From File, click Options.
  2. Click Calendar.
  3. Under Work Time, in the First day of week list, select the day that applies to both the full week and the work week.